THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek.
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.

For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding, This news data comes from:http://www.redcanaco.com
- Fire breaks out in Manila residential area
- Motive probed for US shooting that killed two children, injured 17
- Tourists dice with danger on Hanoi's train street
- Recto: No exemption for US tech firms from digital tax
- Dizon to abolish DPWH internal special investigation team created to look into the flood control anomalies
- Marcos sacks PNP Chief Torre, saying it was 'difficult but necessary'
- Lacson to govt: Protect education budget
- Thai woman jailed for 43 years for lese majeste freed
- Thai cannabis-championing tycoon takes office as PM
- Some areas in Metro Manila, Bulacan to have brownouts due to maintenance work